Description
Critical Path
Prior to beginning work on this learning activity, review the following webpages CPM – Critical Path Method, Gantt Chart, and PERT, and read Chapter 6: Developing a Project Schedule from your course textbook.
Based on the table below, draw a project network from the following information: What activity(s) is a burst activity? What activity(s) is a merge activity? What is the critical path?
Work Packages
IDDescriptionPredecessorDurations
ASurvey SiteNone2 DaysBExcavate SiteA4 DaysCInstall Power LinesB3 DaysDInstall DrainageB2 DaysEPour FoundationC, D3 Days